Pesquisando. PF Aguarde 👍🏽 ...

Landmine clearance completed along high-voltage line

     Society              
  • Luanda • Tuesday, 19 March de 2024 | 09h42
Desminagem na Huíla
Desminagem na Huíla
Morais Silva - ANGOP

Lubango – At least 175.5 kilometres of the Lubango-Caconda route, in Huíla province, have been cleared as part of the implementation of the 400-kV power transmission line from the Belém do Dango substation in Huambo to Lubango.

The project of the High Voltage Line "Belém do Dango – Lubango" has a length of 343 kilometers, 60 in width, with a transit capacity of 2271 MVA at the thermal limit of the conductor cables, it will connect the Belém do Dango substation to the Lubango substation.

The work, which began on November 9, will run until the end of April of this year and during the Lubango-Caconda route, 12 explosive devices of various caliber and 89 rounds of ammunition were collected.

Speaking to ANGOP, the head of the provincial department of the National Demining Center (CND) of Huíla, Tomás Calundungo, said that the work on the section was not only on the road, but in surrounding areas.

As a result of awareness-raising work during the action on the Lubango-Caconda route, he said that 20 detonated devices of various caliber were collected in locations near the route.

According to the source, internal quality control and verification is underway at the Nombungo electrical substation in Arimba, where an expansion is being carried out to ensure greater safety for the machines that are maneuvering in the area.

"At the moment the machine is doing the processing work for the substation and as soon as it is finished, they will hand over the work to the contractor, possibly at the end of April," he said.

He pointed out that during the period, they were faced with constraints caused by the relief of certain areas of the municipality of Cacula, as well as the rains that slowed a little down the work.

The 400 kV Belém do Dango-Lubango line, between the Belém do Dango and Lubango substations, is part of a wider programme of projects aimed at ensuring, essentially, the transmission of production from the Laúca Hydroelectric Power Plant to the northern, central and southern areas of Angola.

The line, after Lubango, goes to the provinces of Cunene and Namibe. MS/MS/CF/DOJ





Top Photos

Presidente Joe Biden visita Angola na primeira semana de Dezembro

Presidente Joe Biden visita Angola na primeira semana de Dezembro

 Thursday, 21 November de 2024 | 12h47

Angolana Maria do Rosário Lima designada embaixadora do G20 Social

Angolana Maria do Rosário Lima designada embaixadora do G20 Social

 Thursday, 21 November de 2024 | 12h43

Início de voos de passageiros no AIAAN marca história da aviação civil  angolana

Início de voos de passageiros no AIAAN marca história da aviação civil angolana

 Thursday, 21 November de 2024 | 12h36

Criadores do Sul de Angola asseguram 80% na redução da importação de carne

Criadores do Sul de Angola asseguram 80% na redução da importação de carne

 Thursday, 21 November de 2024 | 12h32

Aviação Civil angolana premiada pela excelência no Egipto

Aviação Civil angolana premiada pela excelência no Egipto

 Thursday, 21 November de 2024 | 12h24

Angola beneficia de mais de 100 milhões USD para combater alterações climáticas 

Angola beneficia de mais de 100 milhões USD para combater alterações climáticas 

 Thursday, 21 November de 2024 | 12h14

Brasileiros admitem possibilidade de Angola ser celeiro mundial

Brasileiros admitem possibilidade de Angola ser celeiro mundial

 Thursday, 21 November de 2024 | 12h06

Serviços Prisionais aumentam área de produção agrícola no Cunene

Serviços Prisionais aumentam área de produção agrícola no Cunene

 Thursday, 21 November de 2024 | 11h57


News of interest

A pesquisar. PF Aguarde 👍🏽 ...
+