Luachimo dam starts testing equipment

     Economy              
  • Luanda • Tuesday, 09 August de 2022 | 12h48
LUNDA-NORTE: Rehabilitation works of Luachimo dam
LUNDA-NORTE: Rehabilitation works of Luachimo dam
Nelson Malamba

Dundo - The acceptance tests of the equipment to prepare for the start-up of the first two turbines at the Luachimo hydroelectric dam in eastern northern Lunda Norte province started Tuesday (09), the rehabilitation works manager has announced.

Joaquim Costa, director of rehabilitation and expansion works, said the  two turbines, with a capacity to produce 17 megawatts of electricity, have already been installed.

Joaquim Costa also announced the execution of two more turbines, with the same capacity, whose works he said stand above 60 percent.  

Estimated at more than USD212 million, financed by a credit line from China, the works will help increase from 8.4 to 34 megawatts (MW) the power capacity provided by the infrastructure.

The start up of the project, comprising four generators of 8.5 megawatts each, will bring to a total of 34 megawatts, capable to cater to 186,000 residents of the province’s capital, Dundo, and the municipalities of Cambulo and Lucapa, as well as the localities of Fucauma, Cassanguidi, Luxilo and Calonda. 

 





News of interest

Government wants better informed citizens

 Tuesday, 26 November de 2024 | 11h37

Cunene wants more investment in transport

 Tuesday, 26 November de 2024 | 01h24

Ministry of Health resumes IPC program

 Monday, 25 November de 2024 | 23h25

A pesquisar. PF Aguarde 👍🏽 ...
+